This is week 2 repot of what materials we used, any queries and a daily report, this week we have got a lot done and to show the progresses of work. All is on task and work is going smoothly.
Site Daily Report
CNO:
01980
|
Title:
Work Shop Refurbishment
|
Date:04.02.13
Manager:
HARLEY CROOKES
|
TRADE
|
LAB
|
PROGRESS
|
Unibond / plastering
|
Ryan, Taylor. Christian, Blake, Michael
|
In Progress
|
Mixing plaster
|
Ashley Cooke/Matthew King
|
On Going
|
Filling/Plaster boarding support
|
Sam Shrewsbury
|
In Progress
|
WEATHER: Sunny with clouds
|
TIME LOST: N/A
|
Work
in Progress:
|
Bay 4 is having its
first and second coat plastered on my Michael fitchie . Bay 5 has a small piece
of plaster boarding left and will be finished in the morning by Sam
Shrewsbury. Bay 8 is having noggin put
in by Sam Shrewsbury to make it more secure before plaster goes on. Bay 9-10-11
are having there 1st coats of plaster out on my Taylor Measor Ryan
dove and Blake white. Bay 18 has had its second coat put on and is now having
outside of its bay plastered. The Mixing of the plaster is being continuously
done by Matthew king and Ashley Cooke.
CNO:
01980
|
Title:
Work Shop Refurbishment
|
Date:06.02.13
Manager:
MICHAEL FITCHIE
|
TRADE
|
LAB
|
PROGRESS
|
Unibond / plastering
|
Ryan, Harley, Sam, Lewis and Jordan
|
In Progress
|
Mixing plaster
|
Chris and ash
|
On Going
|
Filling/Plaster boarding
|
Blake
|
In Progress
|
WEATHER: Sunny with clouds
|
TIME LOST: N/A
|
Work
in Progress:
|
Bays 3, 6, 14, 17, 19
and 20 are being patched and repaired by Blake White. Outside of Bays 11 and 12
have been plastered by Sam Shrewsbury he has now done 2 side of the bay 11 and
is now prepping the other bays. Bay 9 are
having first coat of plaster on two walls by Ryan. Bay 10 are having first coat
of plaster on two walls by Harley. Lewis is putting first coat of plaster on in
side of bay 8. Chris and ash are mixing up plaster. Jordan pope is plastering
out side of bays 18, 19 and 20 first coat.
CNO:
01980
|
Title:
Work Shop Refurbishment
|
Date:07.02.13
Manager:
Blake white
|
TRADE
|
LAB
|
PROGRESS
|
Unibond / plastering
|
Ryan, Sam, Lewis,brad,mike and Jordan
|
In Progress
|
Mixing plaster
|
Lewis and Sam
|
On Going
|
WEATHER: Sunny with clouds
|
TIME LOST: N/A
|
Work
in Progress:
|
Bays 2,4,9,10,20 all
had seconds coats and we’re all smoothed. In bay 5 Jordan has started to put on
the first coat off plaster and Sam and Lewis have been mixing the plaster for
the rest of the workers to use.
Materials
|
Contract C: 001980
|
Title: Work Shop
Refurbishment
|
Week Ending: 31.1.13
|
Manager: Ryan Wakefield
|
DATE:
|
MATERIAL:
|
quantities
|
04.02.13
|
Solo wood screws 5.0x100mm
|
100
|
04.02.13
|
25kg bag of plaster
|
3
|
04.02.13
|
212cm batten
|
|
7.02.13
|
25Kg bag of plaster
|
5
|
QUERY & INSTRUCTION SHEET
TO;
John Symes
|
|
CONTRACT
NO; 01980 WORKSHOP
REFURBISHMENT
|
|
DATE;6.2.13
|
QI
NO;02
|
QUESTION
Do you have to plasterboard above the
doors if there is a small gap
|
ANSWER
If the architrave Does not cover the
join, you should have allowed for plaster boarding and plastering of it in
your quote.
|