Sunday, 24 March 2013

Project week 2


This is week 2 repot of what materials we used, any queries and a daily report, this week we have got a lot done  and to show the progresses of work. All is on task and work is going smoothly.


Site Daily Report
CNO: 01980
Title: Work Shop Refurbishment
Date:04.02.13
Manager: HARLEY CROOKES


TRADE
LAB
PROGRESS
Unibond / plastering
Ryan, Taylor. Christian, Blake, Michael
In Progress
Mixing plaster
Ashley Cooke/Matthew King
On Going
Filling/Plaster boarding support
Sam Shrewsbury
In Progress








WEATHER: Sunny with clouds
TIME LOST: N/A

Work in Progress:
 Bay 4 is having its first and second coat plastered on my Michael fitchie . Bay 5 has a small piece of plaster boarding left and will be finished in the morning by Sam Shrewsbury.  Bay 8 is having noggin put in by Sam Shrewsbury to make it more secure before plaster goes on. Bay 9-10-11 are having there 1st coats of plaster out on my Taylor Measor Ryan dove and Blake white. Bay 18 has had its second coat put on and is now having outside of its bay plastered. The Mixing of the plaster is being continuously done by Matthew  king and Ashley Cooke.

CNO: 01980
Title: Work Shop Refurbishment
Date:06.02.13
Manager: MICHAEL FITCHIE

TRADE
LAB
PROGRESS
Unibond / plastering
Ryan, Harley, Sam, Lewis and Jordan
In Progress
Mixing plaster
Chris and ash
On Going
Filling/Plaster boarding
Blake
In Progress







WEATHER: Sunny with clouds
TIME LOST: N/A

Work in Progress:
 Bays 3, 6, 14, 17, 19 and 20 are being patched and repaired by Blake White. Outside of Bays 11 and 12 have been plastered by Sam Shrewsbury he has now done 2 side of the bay 11 and is now prepping the other bays.  Bay 9 are having first coat of plaster on two walls by Ryan. Bay 10 are having first coat of plaster on two walls by Harley. Lewis is putting first coat of plaster on in side of bay 8. Chris and ash are mixing up plaster. Jordan pope is plastering out side of bays 18, 19 and 20 first coat.  

CNO: 01980
Title: Work Shop Refurbishment
Date:07.02.13
Manager: Blake white

TRADE
LAB
PROGRESS
Unibond / plastering
Ryan, Sam, Lewis,brad,mike and Jordan
In Progress
Mixing plaster
Lewis and Sam
On Going










WEATHER: Sunny with clouds
TIME LOST: N/A

Work in Progress:
 Bays 2,4,9,10,20 all had seconds coats and we’re all smoothed. In bay 5 Jordan has started to put on the first coat off plaster and Sam and Lewis have been mixing the plaster for the rest of the workers to use.


Materials

Contract C: 001980
Title: Work Shop Refurbishment

Week Ending: 31.1.13
Manager: Ryan Wakefield

DATE:
MATERIAL:
quantities
04.02.13
Solo wood screws 5.0x100mm
100
04.02.13
25kg bag of plaster
3
04.02.13
212cm batten

7.02.13
25Kg bag of plaster
5




QUERY & INSTRUCTION SHEET
TO; John Symes
CONTRACT NO; 01980               WORKSHOP REFURBISHMENT
DATE;6.2.13
QI NO;02

QUESTION
Do you have to plasterboard above the doors if there is a small gap

ANSWER
If the architrave Does not cover the join, you should have allowed for plaster boarding and plastering of it in your quote.





No comments: