This is a weekly repot of what materials we used, any queries and a daily report, this will be every week to show the progresses of work and to keep eye on all stock and work going on.
Site Daily Report
CNO:
001980
|
Title:
Work Shop Refurbishment
|
Date:
30.1.13
Manager
: Ryan
|
TRADE
|
LAB
|
|
Protection
|
Lewis & Michael
|
completed
|
Remove existing P/B
|
Harley & Blake
|
completed
|
Stud Wall
|
Brad & Sam
|
completed
|
Floor Repair
|
Matt & Chris +
|
completed
|
Patch repair
|
Harley & Blake
|
completed
|
Plaster Boarding
|
Harley & Chris & Matt & Blake & Lewis & Michael
|
In progress
|
WEATHER:
|
TIME LOST:
|
Work
in Progress:
|
Protection: Lewis and Michael almost completed protection they will
then move onto plaster boarding.
Remove Old Plaster Board:
Harley & Blake completed bays: 3: two patch repairs, 7: right wall
(small repair) 8: one left side wall and half of the right wall, 9: outside
Cheek of bay, 13: two patch repairs boxing, 14: outside cheek of bay, 15:
outside cheek of bay, 16: outside side wall and cheek of bay. Now filling in
a patch repair.
Stud Wall: Brad & Sam
Floor Repairs: Chris & Matt are in progress of completing the task.
Bays need to be completed: (2,5,11,12,14,19,20) replacing missing
board/s
Bay 6: Floor repair: uses a crow bar to take up a floor board and
used a saw to cut through to make it easier to remove, once that floor board
was removed we pushed back existing floor boards to close gaps in between
each board.
Plaster Boarding is in progress.
|
VISITORS
|
Mitchell M: wanted to annoy John S, No PPE, DID NOT sign in.
|
Ashley Bean: accompanied Mitchell, No PPE, DID NOT sign in.
|
CNO:
01980
|
Title:
Work Shop Refurbishment
|
Date:31.1.13
Manager:
Sam Shrewsbury
|
TRADE
|
LAB
|
PROGRESS
|
Plaster boarding
|
Harley, Blake, Ashley, Matt,
Christian
|
Finished
|
Scrim / beading
|
Lewis, josh
|
Finished
|
Unibond / plastering
|
Christian, brad, Jordan, Michael, Blake
|
On going
|
Door frame
|
Lewis
|
In progress
|
WEATHER: Sunny with clouds
|
TIME LOST: N/A
|
Work
in Progress:
|
Bay 1 has been left for the time being as the ironmongery work is
complete.
Bay 2 has been scrimmed and beaded by Lewis in preparation for
plastering
Bay 3 has been filled today as there was some chips in the walls
Bay 4 has been has been scrimmed by Lewis; Matt fixed one of the
plasterboard repairs.
Bay 5 The door lining has been replaced by Lewis and I have checked
to make sure its all plumb and level etc. it has been scrimmed, also the
floor board needs replacing, Matt strengthened the plasterboard repair.
Bay 6 has had some of the repairs plastered to smooth the wall
Christian has done the second coat
Bay 7 has had some of the repairs plastered to smooth the wall
Christian has done the second coat
Bay 8 has been scrimmed by Lewis. The plastered board needed a few
more screws to strengthen it and matt done this.
Bay 9 Harley has been working in this bay, he has added a piece of
timber to screw plasterboard to and plaster boarded the whole bay, he has
also cut a whole in one of the pieces for access to the light switch, he is
also beaded and scrimmed this bay ready for plastering
Bay 10 has been scrimmed by Lewis
and is ready for plastering, some walls need a second coat the rest
need starting
Bay 11 Ashley has plaster boarded two half walls and around some of
the outside of the bay, This bay has also been beaded by Lewis
Bay 12 Brad has finished off his first coat of plaster and second
coated / polished the majority of this bay
Bay 13 A small patch repair has been plastered and Christian has
second coated the area to make the wall smooth
Bay 14 Brad and Blake began
some first coats in and around this bay of plastering, Michael is doing a
second coat on a bit of plasterboard repair
Bay 15 Jordan has done a second coat on the plasterboard repair and
Christian has polished it, Lewis scrimmed this bay
Bay 16 Nothing has been done to this bay today
Bay 17 Christian has done a first coat of plaster on a small
plasterboard repair
Bay 18 Christian has plastered the two big walls doing first and
second coat, he also polished these walls down, Josh has beaded this bay
Bay 19 Jordan has done two of the walls in first coat
Bay 20 Christian put a first coat on two patch repairs in this bay
Blake, Brad, Harley, Michael, Lewis stayed behind 10 minutes into
their break with me today to help use up the last of the mixed plaster, we
plastered a few patch repairs and any small gaps we could see we put in a bit
of plaster to fill the gap.
Lewis, Blake, Brad and Harley have begun filling any screw holes,
cracks, chips etc. in the walls they can see.
Michael has been more of a labourer today and has mixed all the plaster,
cleaned the buckets and although at times the plasters who finished the wall
gave him some help he has managed to keep up with them and done well keeping
a constant flow of plaster, he also helped second coat some patch repairs.
Josh has been a general labourer today and has been around helping
people by getting more plaster, and put up some beading.
Harley and Matt has fixed the plasterboard around the outside of the
bay, some bits my need tweaking.
Josh made a bin run today.
|
VISITORS
|
Mitchell Macdarmid: Trying to disrupt / disturb Ashley and Jordan. No
ID but had PPE. 10:25-10:33, 11:43-11:51, 12:45-13:00
|
Nicola Sankey: Site visit from team leader to check progress. Had ID
and PPE
|
Andy Benn: Had ID and PPE, come to see how we was getting on. 13:00-
|
Materials
|
Contract C: 001980
|
Title: Work Shop
Refurbishment
|
Week Ending: 31.1.13
|
Manager: Ryan Wakefield
|
DATE:
|
MATERIAL:
|
quantities
|
30.1.13
|
Dry wall screws – 3.5x25mm
|
1000
|
30.1.13
|
Floor board nails
|
100g
|
30.1.13
|
Roll of BPM
|
1
|
30.1.13
|
Duck tape
|
2
|
30.1.13
|
9.5mm plaster board
|
6
|
30.1.13
|
Floor board length 3.6mx90mmx19m
|
2
|
30.1.13
|
Buckets
|
1
|
30.1.13
|
CLS 62mmx38mmx2.4m
|
4
|
31.1.13
|
Scrim
|
1 roll
|
31.1.13
|
Skim beading galvanised 2.4M
|
7 lengths
|
31.1.13
|
Thistle multi finish plaster
|
5
|
31.1.13
|
Plasterboard 9.5mm
|
6
|
31.1.13
|
Par timber 125mmx25mmx5.5m
|
1
|
31.1.13
|
Dry wall screws – 3.5x25mm
|
1000
|
QUERY & INSTRUCTION SHEET
TO;
John Symes
|
|
CONTRACT
NO; 01980 WORKSHOP
REFURBISHMENT
|
|
DATE;
|
QI
NO;01
|
QUESTION: Today we found some
un-noticed problems with the project. In our original Programme we have
missed of the removal and replacement of a door frame and repairing several
other door frames, we also didn’t allow for removing the coat hooks and
shelves that where already in place.
|
ANSWER
In reference to the specification the
door linings are noted and should have been picked up in your survey.
The specification dose not include for
shelving or hooks.
|